Data Analysis - Cube Calculation

K

KarenF

Hi All,

In Project Server 2003, I was able to create a Portfolio Analyzer view
showing cumulative baseline work with a calculation of:
Sum(PeriodsToDate([Time].[Week]),[Measures].[Baseline Work])
This worked very well.
I am trying to re-create this view in Project Server 2007 with the
same calculation. It is not working - the results I get is the
baseline work value for each week- not the cumulative sum.

Does anyone know if I need a different calculation in PS 2007?

Thanks in advance,
KarenF
 
B

Ben Howard

My understanding is the syntax is the same, however P2007 has week dimensions
for financial periods, timesheet periods etc. Worth just checking that the
time.week dimension is the correct one?
 
K

KarenF

My understanding is the syntax is the same, however P2007 has week dimensions
for financial periods, timesheet periods etc. Worth just checking that the
time.week dimension is the correct one?
--
Thanks, Ben.http://appleparkltd.spaces.live.com/



KarenF said:
In Project Server 2003, I was able to create a Portfolio Analyzer view
showing cumulative baseline work with a calculation of:
Sum(PeriodsToDate([Time].[Week]),[Measures].[Baseline Work])
This worked very well.
I am trying to re-create this view in Project Server 2007 with the
same calculation. It is not working - the results I get is the
baseline work value for each week- not the cumulative sum.
Does anyone know if I need a different calculation in PS 2007?
Thanks in advance,
KarenF- Hide quoted text -

- Show quoted text -

Thanks Ben, you're correct. I had to put [time].[all] for it to
work.

KarenF
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top