D
Dots
I have 2 views created in Data Analysis: 1 that pulls from the Timesheet cube
for timesheet data and a second that pulls from EPM Timesheet for hours from
the project plan. My hope was to see that timesheet hours compare to Project
hours. with these 2 views. Unfortunately I am seeing a discrepancy in the
data, although this discrepancy is not consistent. Below is an example of
data being pulled from these two views.
Timesheet Project List Level 02 Project List Level 02
Basis Administration & Support - 2009 829.00 Basis Administration & Support
- 2009 717.00
BI Reporting Corporate - 2009 664.00 BI Reporting Corporate - 2009 664.00
Communication Voice and Data Support - 2009 822.50 Communication Voice and
Data Support - 2009 814.00
In addition to this, if I go back to the project plan, in some instances the
actual work entered does not reflect what is being reported in the project
pull. What's going on here and how do I fix this so that data in my cube is
an actual reflection of data being entered?
Thanks, Dots.
for timesheet data and a second that pulls from EPM Timesheet for hours from
the project plan. My hope was to see that timesheet hours compare to Project
hours. with these 2 views. Unfortunately I am seeing a discrepancy in the
data, although this discrepancy is not consistent. Below is an example of
data being pulled from these two views.
Timesheet Project List Level 02 Project List Level 02
Basis Administration & Support - 2009 829.00 Basis Administration & Support
- 2009 717.00
BI Reporting Corporate - 2009 664.00 BI Reporting Corporate - 2009 664.00
Communication Voice and Data Support - 2009 822.50 Communication Voice and
Data Support - 2009 814.00
In addition to this, if I go back to the project plan, in some instances the
actual work entered does not reflect what is being reported in the project
pull. What's going on here and how do I fix this so that data in my cube is
an actual reflection of data being entered?
Thanks, Dots.