D
Dots
I am experiencing times when a project manager imports reource tasks updates
(Project 2007), republishes the project plan and then after the cube is
rebuilt runs a data analysis report to see actual work against that project,
the actual work hours are not captured correctly in the data analysis cube.
Example: resource enters 2.5 hours against a task, PM accepts those hours.
The hours are shown in the project plan. Manager publishes. next day we
view the data analysis report and those 2.5 hours are not showing against
that task. BUT, if I go back to the project, that task item does have the
2.5 hours in the actual work field.
This is not just hapening on one project, but across random projects and I
need to know why this is happening and how to fix it. Please help!
Dots
(Project 2007), republishes the project plan and then after the cube is
rebuilt runs a data analysis report to see actual work against that project,
the actual work hours are not captured correctly in the data analysis cube.
Example: resource enters 2.5 hours against a task, PM accepts those hours.
The hours are shown in the project plan. Manager publishes. next day we
view the data analysis report and those 2.5 hours are not showing against
that task. BUT, if I go back to the project, that task item does have the
2.5 hours in the actual work field.
This is not just hapening on one project, but across random projects and I
need to know why this is happening and how to fix it. Please help!
Dots