T
TREVOR
I have set up a table in ACCESS to track hours worked on a given project.
The table is updated using the "Collect Data Through Email Messages Wizard."
But I want the incoming data to add to, not over-write, the project hours
previously posted. Is there a way to do that? If so, what is the routine?
Thanks,
Trevor
(e-mail address removed)
The table is updated using the "Collect Data Through Email Messages Wizard."
But I want the incoming data to add to, not over-write, the project hours
previously posted. Is there a way to do that? If so, what is the routine?
Thanks,
Trevor
(e-mail address removed)