C
Charles L. Simpson
I'm hoping to get some help on this issue today as one of my users is trying
to generate a report with this information. If I need to provide any
addition information, please let me know.
On all of my projects, the Finish Variance on PWA and in on the Project
Summary line in Pro are not in sync.
For instance, on this one project the Finish Variance in Project Pro
is -2.94d and on PWA it says that the Finish Variance is -2.35d.
Any ideas as to why these to are not in sync?
Thanks!
--
---------------------------------------------------------------
Charles L. Simpson
ACT, Inc.
---------------------------------------------------------------
Current Setup:
WSS 2.0 (no service packs)
Project Server 2003 SP1
SQL Server 2000 SP3a
FrontPage 2003 SP2
-----------------------------------------------------------------
to generate a report with this information. If I need to provide any
addition information, please let me know.
On all of my projects, the Finish Variance on PWA and in on the Project
Summary line in Pro are not in sync.
For instance, on this one project the Finish Variance in Project Pro
is -2.94d and on PWA it says that the Finish Variance is -2.35d.
Any ideas as to why these to are not in sync?
Thanks!
--
---------------------------------------------------------------
Charles L. Simpson
ACT, Inc.
---------------------------------------------------------------
Current Setup:
WSS 2.0 (no service packs)
Project Server 2003 SP1
SQL Server 2000 SP3a
FrontPage 2003 SP2
-----------------------------------------------------------------