MS Project Server 2003 and Pro 2003.
Hello, I have one project manager who is receiving conflicting data between
Web Access and Professional, for two particular tasks. An example of one of
the tasks is as follows.
PWA
Work Actual Work Remaining Work
16.5 hrs 16.5 hrs 0 hrs
Project Professional
Work Actual Work Remaining Work
12 hrs 11.5 hrs 0.5 hrs
Although the fields are different, the total of the day by day actual work
tally in PWA is equal to the actual work in Project Professional. Any
suggestions? As always, it is appreciated.
Thanks,
dclarcq
Hello, I have one project manager who is receiving conflicting data between
Web Access and Professional, for two particular tasks. An example of one of
the tasks is as follows.
PWA
Work Actual Work Remaining Work
16.5 hrs 16.5 hrs 0 hrs
Project Professional
Work Actual Work Remaining Work
12 hrs 11.5 hrs 0.5 hrs
Although the fields are different, the total of the day by day actual work
tally in PWA is equal to the actual work in Project Professional. Any
suggestions? As always, it is appreciated.