After publishing the updated project file in EPM an error occurred where the
values in the BCWS field are now "0". The Task Usage/ Task Sheet view show
no values at all in BCWS field. The Resource Usage view has the correct
values in the BCWS field. (The last published version is fine) Why are the
values not populating across the various views? Could there be a corruption
in the application? --
Lisa
values in the BCWS field are now "0". The Task Usage/ Task Sheet view show
no values at all in BCWS field. The Resource Usage view has the correct
values in the BCWS field. (The last published version is fine) Why are the
values not populating across the various views? Could there be a corruption
in the application? --
Lisa