I'm in construction, and I'm trying to put together a graph that will show
cost exposure over time for our various subs. Basically, what I want is a
graph that shows running totals for our subcontractors - so if we have a sub
that is on a particular job from 9/10 - 10/15 for 15 million dollars and
another job from 10/3 - 11/2 for 20 million dollars, the sub is exposed for
15 million dollars up through 10/3, 35 million through 10/15, and 20 million
through 11/2. I want to make a graph that would show this data, but for
multiple subs. I'm not sure exactly how to set up an excel graph that would
do this.

Any ideas would be appreciated.
 
S

Sean Timmons

you're looking at a stacked bar chart.

So, you'd have, say, dates running down column A, then time for each project
in columns B through whatever.

click your chart icon up top, select Bar then stacked bar.

Or, you can pick a stacked line.. Whichever you prefer.

You may want to go by weeks rather than days. Makes for less lines.
 
J

JGeis

Sean,

Won't that just show the project duration, not the dollar value attached to
the sub during those durations?
 