D
Dale N
I have changed working time for M - F from the default time to 7am - 12pm &
1pm - 6pm (total 10 hrs): Tools/options/calendar is set to default start time
7am, default end time 6pm, h/day 10hr, h/wk 50 hr.
Project/project info.../ start date = 7/10
task 1 is entered with fixed work = 4hr & duration = 0.4d and generates
start = 7/10; finish = 7/10.
task 2 is entered with fixed work = 6hr & duration = 0.6d and generates
start = 7/10; finish = 7/11
Why is task 2 finish = 7/11 and 7/10? What am I missing?
Thanks
1pm - 6pm (total 10 hrs): Tools/options/calendar is set to default start time
7am, default end time 6pm, h/day 10hr, h/wk 50 hr.
Project/project info.../ start date = 7/10
task 1 is entered with fixed work = 4hr & duration = 0.4d and generates
start = 7/10; finish = 7/10.
task 2 is entered with fixed work = 6hr & duration = 0.6d and generates
start = 7/10; finish = 7/11
Why is task 2 finish = 7/11 and 7/10? What am I missing?
Thanks