The standard version of Project 2003 has a default of month-day-year for
start & finish dates. Does anyone know of a way to change it to
day-month-year?
 
S

Steve Kearon

Project 2003 always uses the system settings for dmy order. You can change
these system settings through the "regional and language options" section of
Windows Control Panel.

Hope this helps
Steve
 