Date getting changed in Copy Paste

I

ice_cold

I have a MS-Project file (file1) and I have received another smal
MS-Project file (file2) from a co-worker. file2 only has 1 task (with
sub-tasks). When I 'copy' this task from file2 and paste it in file
(on a blank line), the tasks and all the details get pasted well, excep
that the "Dates" (Start, Finish etc.) change. Can someone suggest wh
this might be happening
 
R

Rod Gill

Hi,

When pasted, the tasks become new and probably revert to the project start
date. Another possibility is different calendars.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 