date last changed

J

jdolan @ Stellar

I want to go back through my project schedule and see when the last change
was made. I have inherited a schedule that was not carefully dated and
documented.
 
J

JulieS

Hello jdolan,

You can see when a file was last modified by looking at the file
properties. However, that won't tell you what specifically was
changed. If the last user was tracking data correctly, the status
date (Project > Project Information) may give you some guidance
about the last tracking data applied.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"jdolan @ Stellar" <jdolan @ (e-mail address removed)>
wrote in message
news:[email protected]...
 