H
Harmannus
Hallo,
Is it possible to manipulate the outcome of a data substraction with
workingdays?
E.g.
30-01-2005 (=date()) minus 20-01-2005 (=fldDate) is 10 days. Between
30-01-2005 and 20-01-2005 is a weekend (saterday/sunday). So the outcome
should be 8.
Can the outcome of 8 be generated through code?
Thanx for any tips!
Regards,
Harmannus
Is it possible to manipulate the outcome of a data substraction with
workingdays?
E.g.
30-01-2005 (=date()) minus 20-01-2005 (=fldDate) is 10 days. Between
30-01-2005 and 20-01-2005 is a weekend (saterday/sunday). So the outcome
should be 8.
Can the outcome of 8 be generated through code?
Thanx for any tips!
Regards,
Harmannus