Date of completion of the task

P

Paulo

Where can I got the historical of a task, namely, the completion task? In
other words, is it possible to know, without generating a new baseline, what
was the %complete of a task in a specific date?

Thanks in advance
Paulo
 
P

Paulo

Yes, it helps!

Thank you.
Paulo

Dale Howard said:
Paulo --

It sounds like you are using the % Work Complete method for tracking
progress. This method is not date-sensitive and is the source of your
problem. You must add the Actual Start and Actual Finish columns to each
user's timesheet in PWA. Refer to the following link for the solution to
your problem:

http://www.projectserverexperts.com/Shared Documents/changestartandend.htm

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top