Set the Project start date OR end date in Project -> Project Information.
You may set one or the other not both. MS Project will calculate the date you
did not specify based upon your task schedule.
Set the Project start date OR end date in Project -> Project Information.
You may set one or the other not both. MS Project will calculate the date you
did not specify based upon your task schedule.
Sorry, didn't realize you were looking for the VBA answer. I have *very*
limited knowledge of VBA, but when I recorded the steps for setting the start
date, the resulting code was:
ProjectSummaryInfo Start:="1/10/05"
Hope this helps.
Julie
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.