Date / Time format

  • Thread starter Sequoia D. Schroeder
  • Start date
S

Sequoia D. Schroeder

Is there a way in Project Standard 2002 to have a
DIFFERENT date & time format (for Start/Finish) for each
schedule? I have one schedule where time of day is
important, and another where it is not desired.

Thanks,

Sequoia
 
R

Rod Gill

Hi,

Select View, Table, More Tables
Copy the Entry table and name it "Entry Date and Time"
Here you can select a date format for the table - select one with time.

Create a table for Date only format.

Select the relevant table for your view or create a view for each project
and in More Views select the appropriate table for the report/view
--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
S

Sequoia D. Schroeder

Thanks! Works like a charm.

- Sequoia
-----Original Message-----
Hi,

Select View, Table, More Tables
Copy the Entry table and name it "Entry Date and Time"
Here you can select a date format for the table - select one with time.

Create a table for Date only format.

Select the relevant table for your view or create a view for each project
and in More Views select the appropriate table for the report/view
--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/



.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top