J
JNB
Hello all,
Status Date uses "default end time" of the current project as its default
time; e.g. 02/27/09 17:00 (17:00 is the value on the Default end time box).
Given the above status date with time, what are the date with time figures
for the following ?:
- "spread to at least the day before the status date"
- "midnight on the day before the status date"
Maybe this level of precision is not required for tracking purposes since
MSP will update accordingly as soon as we enter actual values anyway. I have
tried to test the threshold times and it does not seem to work correctly.
I would appreciate any feedback. Thanks in advance.
Best Regards.
JNB
Status Date uses "default end time" of the current project as its default
time; e.g. 02/27/09 17:00 (17:00 is the value on the Default end time box).
Given the above status date with time, what are the date with time figures
for the following ?:
- "spread to at least the day before the status date"
- "midnight on the day before the status date"
Maybe this level of precision is not required for tracking purposes since
MSP will update accordingly as soon as we enter actual values anyway. I have
tried to test the threshold times and it does not seem to work correctly.
I would appreciate any feedback. Thanks in advance.
Best Regards.
JNB