A
ahlroth
Hello,
I have a problem that is making me somewhat crazy. Whenever I change,
for example the hours of an activity, everything else chenges
automatically. I know what the different tasktypes are and what they
mean but there is something else related to this. The activity for
example is 85 hours long, 11 days long and the resource units should be
about 100 percent, nothing special, but I just cant get these three
parameters to have these numbers. There are alot of activities in the
projectfile so there are some dependencies somewhere that are affecting
my activities.
I know that there is not a standard way of solving this but I guess
this happens alot and maybe there are some tips when these problems
occur that I could use?
Thanks for your help.
Regards,
Nicklas
I have a problem that is making me somewhat crazy. Whenever I change,
for example the hours of an activity, everything else chenges
automatically. I know what the different tasktypes are and what they
mean but there is something else related to this. The activity for
example is 85 hours long, 11 days long and the resource units should be
about 100 percent, nothing special, but I just cant get these three
parameters to have these numbers. There are alot of activities in the
projectfile so there are some dependencies somewhere that are affecting
my activities.
I know that there is not a standard way of solving this but I guess
this happens alot and maybe there are some tips when these problems
occur that I could use?
Thanks for your help.
Regards,
Nicklas