Dates are not in sync

M

Mukul Jain

Hi,

I am migrating Project Server 2003 data into Project Server 2007, After
migration project created dates are not matiching with 2003 projects. It is
taking migration date as the project created date in 2007.

Is this a known issue?
 
D

Dale Howard [MVP]

Mukul --

When dates start moving after importing a Project Server 2003 project into
the Project Server 2007 system, this is usually caused by differences
between the calendars used in the 2003 system and the 2007 system.
Specifically, does the Standard calendar used in the 2003 system have the
same nonworking time periods as those specified in the 2007 system? If not,
that in itself will cause dates to change in the projects after they are
imported. Please examine the calendars carefully in each system. Then let
us know and we will try to help.
 