Sameer
WHen i import a project to the enterprise, the dates are changing for some
tasks,
For eg.
In my .mpp file i have some tasks which are 1 day and they start on sat and
finish on sat itself.
Once i import it the duration remain at one day and even the start is one
sat but the finish is shifted to sun.
Can any one help me on this,
Regards