Hi

I created a project (non -enterprise) when i published, The whole project
dates got shifted. I need to revalidate around 300 line items and adjust.
This is a massive rework which I can not carry.

is there any way to way to upload the project intact.

regards
Gopi
 
A

Aaron Tamblyn

If your Project Server is set to allow local base calandars in the Server
Configuration page then you could import your local plan to project server
using Tools > Enterprise Options > Import Project to Enterprise...
This would get you plan into the system BUT I would not suggest this
normally.

The normal practice for creating a project schedule would be to connect to
Project Server and create a schedule from an Enterprise Template. You could
then add your resources from the Enterprise resource pool. If you need to
work disconnected, you can take the project offline at this point (File >
Save Offline) and build up the schedule and create assignments. Later when
you connect to Project Server, you can save the file online.
 