Dates to Workdays in Network Diagrams

L

Led

How do I display the network diagram with the early start day and early
finish day for each activity as opposed to the date of the activity. I.e.
early start is day 1 of project, activity 2 starts on day 7 of project, etc.
 
J

JulieS

Hello Led,

You can edit the date format in the Network Diagram view through the
Format > Box Styles or the Format > Box command. I assume you want to
change multiple boxes, so I'd suggest Format > Box Styles. You'll need
to select each box style (Critical, Noncritical, etc.) in turn. Click
the More Templates button and either edit the template if possible (the
"standard" template cannot be edited, just copied and renamed). Once
you are editing the template and showing the Data Template Definition,
click on the cell in the preview with the date and change the date
format.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 