I developing a small project plan in excel - starting with project end date
and subtracting task durations to get to start date. Using
=DATE(YEAR(D30),MONTH(D30),DAY(D30)-C29) to get to the next earlier date.
Problem is I need to exclude weekend dates. D30=end date. C29=duration of
task. How do I do that?