day one

L

L

How do I start a project on month one , day one and
progress thru day two , day three etc.?
 
J

John Beamish

P2002/3 (and others?)

1. Tools | Options | and set the date format to "W5/1" (this shows dates in
a week/day format where w1/1 is week 1, day 1; w2/3 is week 2, day 3).

2a. RightMouseButton on the date "bars" above the Gantt chart and click on
Timescale. For Timescale options, choose "3 tiers (Top, Middle, Bottom)"

2b. Click on the Top Tier tab; select Units as "Months"; select Count as 1;
select Label as "Month 1, Month 2 ... from start"
2c. Click on the Middle Tier tab; select Units as "Weeks"; select Count as
1; select label as "Week 1, Week 2 ... from start"
2d. Click on the Bottom Tier tab; select Units as "Days"; select Count as
1; select label as "D1, D2, D3 from start"

JLB, PMP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top