T
The Evaluator
Daylight Savings Time patch didn't work, it states there are no problems.
I installed all of the patches from this Microsoft link already
http://support.microsoft.com/default.aspx/gp/dst_prodlist
This issue for my work here is only affecting the calander in mid MARCH and
early APRIL only. For example, USER1 sends an invite for meeting at 2pm.
USER2 recieves the invite as 3pm.
I'm trying to avoid manually changing everyone's meetings, but I think I may
have to do that. I support about 50+ users.
Thanks
I installed all of the patches from this Microsoft link already
http://support.microsoft.com/default.aspx/gp/dst_prodlist
This issue for my work here is only affecting the calander in mid MARCH and
early APRIL only. For example, USER1 sends an invite for meeting at 2pm.
USER2 recieves the invite as 3pm.
I'm trying to avoid manually changing everyone's meetings, but I think I may
have to do that. I support about 50+ users.
Thanks