Days of Week in Wrong Order

N

Nils

My days of the week are showing up in order of Monday, Wednesday, Friday,
Sunday, Tuesday, Thursday, Saturday. I have tried manipulating this but
nothing seems to work. This is very strange. If I start a new project, the
days show up correctly. Is there anything I can do to fix this?
 
W

Wiley

Nils,

The only way i know you could be seeing this is in the Gantt chart on the
right. The days are not really out of order. You are just seeing every
other day. Right click on the header in the Gantt chart and select
Timescale.. Go to the tab for days (most likely the Bottom Tier tab). The
Count probably show "2". Change it to "1". All days will show now.

This calendar alos is set to start on Monday. If you prefer it to start on
Sunday, go to Tools -> Option ->Calendar, and change it there.

Hope this helps.
 
N

Nils

Problem Solved - my bottom tier "Count" got set to 2 somehow (Late night I
guess) I didn't realize that it was showing every other day (in order :)
). Thanks
 