P
Patrick
Hi all. I am in desperate need for help!!
I have a MS Project file that has over 3000 activities. It is built in such
a way that all tasks that have no predecessor start at the beginning of the
project, so MS Project can level them later. There are no resources
allocated on tasks for more than the maximum allowed in the resource sheet,
so this is not the cause of the delays.
The project was created by inserting the WBS and activities first, then
dependencies, then work and resources. Tasks are all Fixed Work, so that the
duration can be determined by MS Project. Basically, the question I am asked
to answer is "When is this project going to finish?"
An example of the problem I am getting is that Suzanne, Robert & Steve are
assigned 85% on a task. They maximum is 95% and they are also assigned at
10% on another task that goes from project start to its very end (concurrent
to the task on which they are assigned 85%). After the levelling, the task
on which they are assigned is suddenly broken (split) and then there is a 3
month delay. I thought it was due to the fact that one of them was assigned
on another task, thus delaying other resources, but it is not the case
apparently. They are all halted for 3 months.
Of course, I checked all dependencies and calendars. So, these are also not
the source of the problem.
1. How can I unsplit all tasks all at once? Don't want to do thousands of
tasks manually...
2. Why am I getting this kind of delay (3 month in the example)?
3. I still have sometimes residual data of the levelling. MS Project and
Alzeimer seems to have things in common. How do you COMPLETELY delete
levelling data, so that you start from a fresh set of data, as entered
initially.
BTW, I am clearing the levelling every time and deleting the colomn (audit
delay).
Thanks,
I have a MS Project file that has over 3000 activities. It is built in such
a way that all tasks that have no predecessor start at the beginning of the
project, so MS Project can level them later. There are no resources
allocated on tasks for more than the maximum allowed in the resource sheet,
so this is not the cause of the delays.
The project was created by inserting the WBS and activities first, then
dependencies, then work and resources. Tasks are all Fixed Work, so that the
duration can be determined by MS Project. Basically, the question I am asked
to answer is "When is this project going to finish?"
An example of the problem I am getting is that Suzanne, Robert & Steve are
assigned 85% on a task. They maximum is 95% and they are also assigned at
10% on another task that goes from project start to its very end (concurrent
to the task on which they are assigned 85%). After the levelling, the task
on which they are assigned is suddenly broken (split) and then there is a 3
month delay. I thought it was due to the fact that one of them was assigned
on another task, thus delaying other resources, but it is not the case
apparently. They are all halted for 3 months.
Of course, I checked all dependencies and calendars. So, these are also not
the source of the problem.
1. How can I unsplit all tasks all at once? Don't want to do thousands of
tasks manually...
2. Why am I getting this kind of delay (3 month in the example)?
3. I still have sometimes residual data of the levelling. MS Project and
Alzeimer seems to have things in common. How do you COMPLETELY delete
levelling data, so that you start from a fresh set of data, as entered
initially.
BTW, I am clearing the levelling every time and deleting the colomn (audit
delay).
Thanks,