Deadline format

C

CFL

I would like to display a deadline (little green arrow) which puts a line
down the entire gantt chart; ideally i dont want the deadline to appear as a
"task" as it is for information only.

Please help!
 
J

John

CFL said:
I would like to display a deadline (little green arrow) which puts a line
down the entire gantt chart; ideally i dont want the deadline to appear as a
"task" as it is for information only.

Please help!

CFL,
The best you can do is to use the drawing toolbar and manually draw a
vertical line. It can be attached to a deadline milestone so it will
track if the deadline is moved.

John
Project MVP
 
M

Mike Glen

Hi CFL,

If your deadline happens to also be the Project Finish date, you can select
this in Format/Gridlines... Otherwise, as John said.

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 