I'm in MS Project 2003 and use the Task Usage view 95% of the time. I set
deadlines on milestones and depend on the deadline indicator red exclamation
point to alert me if I'm going to miss a deadline. But the indicator does not
always appear even when the finish date and deadline date don't match.
Any ideas why this might be? It's a crucial buy-in point for my account
managers.
Thanks!