M
Michele
I am scheluding a project from an end date.
I have my critical chain made of some certain tasks, a critical chain that
tells me when i have to start the first task of the chain, in other words it
tells me the start date of the whole project.
I create another task, called for example "y", with defaulted constraint
equal to "As late as possible" and without any relations with all the other
tasks.
I associate to the task "y" a deadline date earlier than the end date of the
project and Microsoft Project programs correctly my task "y" calculating its
start backward from the deadlind date.(And after that the task "y" has an
amount of total slack so it's not critical, that is its late start is later
than the start date of the project).
So i have my project correctly scheduled by Microsoft Project, exactly as i
wanted to plan it.
The big problem starts when i associate to task "y" an actual amount of work.
This is the situation:
When i associate to task "y" a percentage of actual work(So without changing
any other parameter of the task(date, constraints, deadline date or anything
else)) Microsoft Project incredibly splits my task "Y" in the next way:
It makes start my task "Y" as scheduled at the beginning but it splits the
task "y" from the start date to the deadline date with 0 percentage of actual
work and it starts counting the percentage of actual work from the deadline
date on, making end the task clearly later than how i programmed at the
beginning.
Beside that it also tells me that my task has a finish date that is later
than my deadline,and this is really incredible because MS project makes all
this incredibly splitting delaying the end of my task all its own and it also
tells me that the task is later than the deadline date!
Two are the possible cases:
1)This is a big bug of Microsoft Project
2)I must have greatly misunderstood some Project behaviour and i would be
very, very gratefull to anyone who will explain where i am wrong, or the
meaning of this point
Really thank u for reading me
Best regards
Michele
I have my critical chain made of some certain tasks, a critical chain that
tells me when i have to start the first task of the chain, in other words it
tells me the start date of the whole project.
I create another task, called for example "y", with defaulted constraint
equal to "As late as possible" and without any relations with all the other
tasks.
I associate to the task "y" a deadline date earlier than the end date of the
project and Microsoft Project programs correctly my task "y" calculating its
start backward from the deadlind date.(And after that the task "y" has an
amount of total slack so it's not critical, that is its late start is later
than the start date of the project).
So i have my project correctly scheduled by Microsoft Project, exactly as i
wanted to plan it.
The big problem starts when i associate to task "y" an actual amount of work.
This is the situation:
When i associate to task "y" a percentage of actual work(So without changing
any other parameter of the task(date, constraints, deadline date or anything
else)) Microsoft Project incredibly splits my task "Y" in the next way:
It makes start my task "Y" as scheduled at the beginning but it splits the
task "y" from the start date to the deadline date with 0 percentage of actual
work and it starts counting the percentage of actual work from the deadline
date on, making end the task clearly later than how i programmed at the
beginning.
Beside that it also tells me that my task has a finish date that is later
than my deadline,and this is really incredible because MS project makes all
this incredibly splitting delaying the end of my task all its own and it also
tells me that the task is later than the deadline date!
Two are the possible cases:
1)This is a big bug of Microsoft Project
2)I must have greatly misunderstood some Project behaviour and i would be
very, very gratefull to anyone who will explain where i am wrong, or the
meaning of this point
Really thank u for reading me
Best regards
Michele