J
Joaquim Amado Lopes
Greetings.
I have 2 tasks (T1 and T2), same duration, no constraints (as soon as
possible) nor predecessors. Both tasks use the same resource (R1).
Only one unit of the resource is available.
Leveling automatic and leveling order "standart" or "priority,
standard" (same result).
Naturally, one of the tasks (the one with the higher ID) slips, as
there is only one resource available.
But, if I set a deadline to the task that is schedulled for earlier,
this task slips and is the other one that is done earlier, even if it
causes a conflit with the deadline.
This happens both in:
Project Standard 2002 (10.0.2104.1305) SP-1
Project Professional 2003 (11.0.2003.0816.15)
Tried it with more tasks and those with a deadline slip to as late as
possible. Seems like Project is actually trying to miss the deadlines.
Shouldn't it be the other way around?
Thank you for help,
Joaquim Amado Lopes
I have 2 tasks (T1 and T2), same duration, no constraints (as soon as
possible) nor predecessors. Both tasks use the same resource (R1).
Only one unit of the resource is available.
Leveling automatic and leveling order "standart" or "priority,
standard" (same result).
Naturally, one of the tasks (the one with the higher ID) slips, as
there is only one resource available.
But, if I set a deadline to the task that is schedulled for earlier,
this task slips and is the other one that is done earlier, even if it
causes a conflit with the deadline.
This happens both in:
Project Standard 2002 (10.0.2104.1305) SP-1
Project Professional 2003 (11.0.2003.0816.15)
Tried it with more tasks and those with a deadline slip to as late as
possible. Seems like Project is actually trying to miss the deadlines.
Shouldn't it be the other way around?
Thank you for help,
Joaquim Amado Lopes