G
Gary Zag
We use My Tasks for resources to get their work assignments. We would like
these resources to try to meet the scheduled finish date that is shown when
they are first assigned the task. The problem we are having is the finish
date changes when the person updates their task information with hours
different than planned or when they adjust the remaining hours. Is there any
way to display the original finish date (original deadline) along with the
adjusted finish date.
Gary
these resources to try to meet the scheduled finish date that is shown when
they are first assigned the task. The problem we are having is the finish
date changes when the person updates their task information with hours
different than planned or when they adjust the remaining hours. Is there any
way to display the original finish date (original deadline) along with the
adjusted finish date.
Gary