M
Marc
Hello,
Has anyone come across (or have any ideas) on how to deal with tracking
consulting projects. When I try to get estimates of work for a project,
the consultants give me dates based on duration. E.g. it will take 1
month to complete task A. Effort is seldom measured. (I'm on an
uphill battle for change but as you may know, changes do not come easy)
Is there any way to track a project based on duration rather than
effort. Specifically, is there any way that I can keep the start and
end date from changing even though there is effort put into the project
plan? We use Central Project Office as our time tracking tool and it
automatically updates effort to the project plan each week. I am
constantly manually updating the dates but I'd like to only do this
when I know there will be a change to the duration in the project.
Thanks in advance.
Marc
Has anyone come across (or have any ideas) on how to deal with tracking
consulting projects. When I try to get estimates of work for a project,
the consultants give me dates based on duration. E.g. it will take 1
month to complete task A. Effort is seldom measured. (I'm on an
uphill battle for change but as you may know, changes do not come easy)
Is there any way to track a project based on duration rather than
effort. Specifically, is there any way that I can keep the start and
end date from changing even though there is effort put into the project
plan? We use Central Project Office as our time tracking tool and it
automatically updates effort to the project plan each week. I am
constantly manually updating the dates but I'd like to only do this
when I know there will be a change to the duration in the project.
Thanks in advance.
Marc