I am of the self learner of Microsoft project. Please could you help me how
to manage the following.
Let us assume there is 1000 m2 of blockwork is necessary to build a room.
For m2 of Blockwork let us take A Nos of blocks+ B Nos of Bags of Cement + C
kgs of Sand + D Ltrs of Water +E sets of Scaffolding+F Nos of Masons + G Nos
of helpers are required.
I know clearly howmuch per m2 of to do the blockwork as specified above. If
I want maintain track or to know howmuch qty of above material is required
for specified %work,how can I mange these things in MS project.
Pl. advice me with the same example

Thanking you sir,
D.Jayadevaraju
 
J

Jan De Messemaeker

Hi,

Although one might find a solution to this, I'm afraid you are not in the
right product to do this.
This is a Bill of Material problem, and Project doesn't handle that out of
the box.
Project's main tasks is to calculate start and end dates of tasks you
specify, taking into account external constraint, links between tasks, and
availability of work resources (not even material resources).

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
"How to solve the following problem" <How to solve the following
(e-mail address removed)> schreef in bericht
news:[email protected]...
 
Top