Decimal Actual work protected

  • Thread starter Needhi rajan John williams
  • Start date
N

Needhi rajan John williams

I approve 7 hrs for a day for a resource in PWA , it appears as 7.33 hrs in the project pro next time I open.

The same is the case for few other tasks it becomes 8.66 etc..

What could be the reason

Thanks in advance

Needhi Rajan PMP

EggHeadCafe.com - .NET Developer Portal of Choice
http://www.eggheadcafe.com
 
G

Gaurav Wason

Nidhi,

What kind of task do you have in project professional? Did you tried sync
with protected actuals option.

Please let me know.
--
Gaurav Wason
(e-mail address removed)
MCP - Project Server
Project Made Easy
Project Archive Tool
Project Owner Tool
http://projectmadeeasy.com
 