Hi,
You need to write and run a VBA macro to do this. Try running the attached
on a copy of your schedule:
Sub test()
Dim T As Task
For Each T In ActiveProject.Tasks
If Not T Is Nothing Then
T.Duration = Round(T.Duration / 60 / ActiveProject.HoursPerDay,
0) * 60 * ActiveProject.HoursPerDay
End If
Next T
End Sub
--
For VBA posts, please use the public.project.developer group.