C
Cole
I just started a project and adopted a schedule with the below formula.
No one knows the intent of the formula which is in a Number Field...can
you guys help me decipher it?
Start is the 'Start Date'
Start 2 is the 'Status Date' (it's set every month)
I understand the first part says if the Status Date is more than one
month of the Start Date.
It's the part that follows I'm having a hard time deciphering.
Is the (1.946/7) and (1.82/7) a common formula in MS Project?
IIf((Start2-Start)>32,([Start2]-[Start])-((1.946/7)*(Start2-Start)),([Start2]-[Start])-((1.82/7)*(Start2-Start)))
Thanks for the help.
No one knows the intent of the formula which is in a Number Field...can
you guys help me decipher it?
Start is the 'Start Date'
Start 2 is the 'Status Date' (it's set every month)
I understand the first part says if the Status Date is more than one
month of the Start Date.
It's the part that follows I'm having a hard time deciphering.
Is the (1.946/7) and (1.82/7) a common formula in MS Project?
IIf((Start2-Start)>32,([Start2]-[Start])-((1.946/7)*(Start2-Start)),([Start2]-[Start])-((1.82/7)*(Start2-Start)))
Thanks for the help.