Hi
We are running Project Server 2007 SP1 with project professional 2007
SP1 client.
A power user has asked that we de-couple project expenditure from
project completion.
Projects currently have the need to have project completion to be run
separatly from the spend on a project, such that if a project is 10%
complete it may have actually spentr 25 % of the budget. Currently
projects assume that 25% of project = 25% of budget, whi8ch is not
what we want.
Is this a project server issue or a project professional issue and
does any one have any suggestiosn about how to set it up as we need
please?
Thanks in advance,
SD.
We are running Project Server 2007 SP1 with project professional 2007
SP1 client.
A power user has asked that we de-couple project expenditure from
project completion.
Projects currently have the need to have project completion to be run
separatly from the spend on a project, such that if a project is 10%
complete it may have actually spentr 25 % of the budget. Currently
projects assume that 25% of project = 25% of budget, whi8ch is not
what we want.
Is this a project server issue or a project professional issue and
does any one have any suggestiosn about how to set it up as we need
please?
Thanks in advance,
SD.