Decoupling % complete from % budget spent

S

sqldude7777

Hi

We are running Project Server 2007 SP1 with project professional 2007
SP1 client.

A power user has asked that we de-couple project expenditure from
project completion.
Projects currently have the need to have project completion to be run
separatly from the spend on a project, such that if a project is 10%
complete it may have actually spentr 25 % of the budget. Currently
projects assume that 25% of project = 25% of budget, whi8ch is not
what we want.

Is this a project server issue or a project professional issue and
does any one have any suggestiosn about how to set it up as we need
please?

Thanks in advance,

SD.
 
M

Mike Glen

Hi SD,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top