O
obrady
Hello,
I have a project with a number of tasks linked with start-to-start lag
times. The problem is however, that decreasing the lag time of a task
will not make the start date earlier, except for first task to have a
lag time link.
Increasing the lag time does result in the start date of a task being
later, and once you have done this you cannot get it earlier again, even
if you set the lag time back to what it orginally was.
A little diagram to help make my issue clearer:
Task 1. Stage 1 starts 4/5/09
Task 2. Stage 1a starts 4/5/09
Task 3. Stage 1b starts 11/5/09 predecessor 2SS+5
Task 4. Stage 1c starts 25/5/09 predecessor 3SS+10
If I change Task 3's predecessor to 2SS+2, it moves the start date back
correctly. But if I change Task 4's predecessor to 3SS+5 it will not
change the start date. If I change the predecessor to 3SS+15 it will
change the start date, but then I can't get it back to the original
again!
I have made sure that auto calculation is turned on and made sure there
are no constraints by setting everything to "As Soon As Possible". Is
there anything else I can check to find out what is forcing these dates
the way they are?
Thanks for any help you can provide.
I have a project with a number of tasks linked with start-to-start lag
times. The problem is however, that decreasing the lag time of a task
will not make the start date earlier, except for first task to have a
lag time link.
Increasing the lag time does result in the start date of a task being
later, and once you have done this you cannot get it earlier again, even
if you set the lag time back to what it orginally was.
A little diagram to help make my issue clearer:
Task 1. Stage 1 starts 4/5/09
Task 2. Stage 1a starts 4/5/09
Task 3. Stage 1b starts 11/5/09 predecessor 2SS+5
Task 4. Stage 1c starts 25/5/09 predecessor 3SS+10
If I change Task 3's predecessor to 2SS+2, it moves the start date back
correctly. But if I change Task 4's predecessor to 3SS+5 it will not
change the start date. If I change the predecessor to 3SS+15 it will
change the start date, but then I can't get it back to the original
again!
I have made sure that auto calculation is turned on and made sure there
are no constraints by setting everything to "As Soon As Possible". Is
there anything else I can check to find out what is forcing these dates
the way they are?
Thanks for any help you can provide.