decreasing the duration of a task pushes my date forward

B

Bob C.

Barb said:
How do I get it to stop doing that?

If you mean that the task ends sooner, therefore the project ends sooner,
you can either enter a lag time (i.e. 16FS+4d) or a "must finish on"
constraint, or make the successor have a "start no earlier than" constraint.

I hope that helps!

-Bob C.
 
J

JulieS

Barb,

What date? The start date of the task? The start date of the
successor? The end date of the project? what do you mean by "pushes
date forward" -- earlier in the schedule?

We'll need more meaningful information from you to be able to help.
Let's start with:

What version of Project?
What service pack?

Please describe in detail what you are doing, what you are seeing,
and what you expected and we'll do our best to assist.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top