For a particular project I would like Project to use an alternate rate table
for a resource. Instead of editing the Cost Rate Table for each task can I
somehow set a default for the whole project?

Thanks,

Mike Einhorn
 
J

John

Mike Einhorn said:
Hello,

For a particular project I would like Project to use an alternate rate table
for a resource. Instead of editing the Cost Rate Table for each task can I
somehow set a default for the whole project?

Thanks,

Mike Einhorn

Mike,
Since you imply the alternate rate is for a given resource why not
simply set that resource's rate appropriately?

Cost rate table information only applies to assignments which are
viewable on either the Resource or Task Usage views. Unfortunately there
is no default setting to do what I think you want. It could be done with
a VBA macro but other than that I think you're stuck with manual entry
for each assignment.

John
Project MVP
 
J

Jan De Messemaeker

Hi,
In resource usage view, show the cost rate table column, set the appropriate
CRT for the first assignment of the reosurce, then drag this value down for
all the resource's assignments.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availabliy check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top