Hello, here is a problem I have tried to resolve:
I have tree ressources A, B and C that I configured the Default Assignment
Manager to be X.
A, B and C don't see their Assignment in "My Task".
X does see all the assignments in "My Task".
A, B and C do see theirAssignment in "My Timesheet", they have fill and
submit the timesheet.
How do X will procedd to update "My Task" for the A, B and C task if
"Project Server" is configured for "Entry by timesheet only"?
Hope, that someone know.