Hisham
I have created a new base calendar other than the default seeded
calendar(Standard). When creating a new project, I do update the project
information by selecting the new base calendar instead of the Standard one.
However, MS Project still assigns the seeded Standard calendar as the
default when creating a new task or when creating a new resource. Is there
anyway to set the new base calendar as the default one when creating a new
task or when adding a new resource?
I appreciate any support on this regard.
Regards,
Hisham.