Andrew,
The none option sounds like you are referring to the Task
Information>Advanced>Task Calendars option. If you want to make your custom
calendar the default for new projects consider creating a new template file
that would have your custom calendar as its base calendar.
I did write an article years ago describing the benefits of what I called a
Company Standard Template, if you send me an email I can send you a copy.
Best way to get in touch with me would be by using the contact option on my
website.
--