default method for reporting progress on tasks does not work

B

Ben

"Hi,

I set up Project WEB Access for reporting time using "Hours of work done per
day or per week", but when I try to reporting times it is still allowing
entry only by percentage. Why is it doing that?

Thanks
 
S

Sara - EPM

Hi Ben,

Once you make the change on PWA/Admin, you must republish your projects.

Team members should be able to post their hours.

Sara
 
B

Ben

Thanks, it is working now

Sara - EPM said:
Hi Ben,

Once you make the change on PWA/Admin, you must republish your projects.

Team members should be able to post their hours.

Sara
 