T
TroyS
Under the 2nd option of Actual Work and Work Remaining....
Though Managed Periods is not turned on, is this Actual work per period as
displayed in the Tasks page?
OR is this Actual Work for the entire project (ie Cumulative)?
For example, i submit 20h on one occasion and approve into the project
The next occasion, i submit 40h...and approve it
Is the Actual Work in the Project Schedule suppose to be 60h (20h + 40h) or
will it be only 40h
Seems odd that under this scenario that Actual Work would cumulative to that
task rather than an amount submitted per period.
thx.
Though Managed Periods is not turned on, is this Actual work per period as
displayed in the Tasks page?
OR is this Actual Work for the entire project (ie Cumulative)?
For example, i submit 20h on one occasion and approve into the project
The next occasion, i submit 40h...and approve it
Is the Actual Work in the Project Schedule suppose to be 60h (20h + 40h) or
will it be only 40h
Seems odd that under this scenario that Actual Work would cumulative to that
task rather than an amount submitted per period.
thx.