Default Resource Graph Format Details

A

andrewandrew

Can I set up the resource graph to default to the Work details instead of
Peak Units?

Cheers!

Andrew
 
J

John

andrewandrew said:
Can I set up the resource graph to default to the Work details instead of
Peak Units?

Cheers!

Andrew

Andrew,
Sure, from the Resource Graph view, go to Format/Details and chose Work.
Then save the file. It will now open with work as the default in the
Resource Graph view.

Hope this helps.
John
Project MVP
 