M
Margaret
I am using Project Server 2007 SP1 and Dec CU. When I create a new task in a
schedule the default Start date is appearing 1/15/10 even thought the Project
information is indicating a start date of November 24, 2008. Is there a
particular setting or a relationship in tasks that I should be looking at to
resolve this issue?
schedule the default Start date is appearing 1/15/10 even thought the Project
information is indicating a start date of November 24, 2008. Is there a
particular setting or a relationship in tasks that I should be looking at to
resolve this issue?