D
dee
Hi,
I have changed the Project calender and the Working time Standard Calendar
to start Mon - Fri at 9 instead of 8 a.m.
All tasks respect this when I add them, except Recurring tasks. They
maintain the default of 8:00 a.m.
Any idea why and how to resolve?
Thanks!
I have changed the Project calender and the Working time Standard Calendar
to start Mon - Fri at 9 instead of 8 a.m.
All tasks respect this when I add them, except Recurring tasks. They
maintain the default of 8:00 a.m.
Any idea why and how to resolve?