Toby:
You can set the tracking method for Project Server globally or locally. If
you want to lock this down at the Server, you can choose the option to force
Project Managers to use the method set by the Project Server Admin. On the
server side (2003), you control this from Admin > Customize Project Web
Access. On the client side, the corresponding settings are controlled from
Tools > Customize > Pulished Fields.
--
Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts
-
Toby said:
Hi all,
How do I default in the timesheet view under the Task section of MS Web
Access to display "day" instead of "week"?